Master Plan - March 14 2006
|
Currently the gym itself is under roof, all light fixtures are in, concrete bleachers have been poured and the steel roof is being set on the fitness corridor. Within ten to fifteen days the entire gymnasium structure will be weather tight, thus allowing dry wall and finishes to be started. The building contains new locker rooms, a fitness room, athletic offices and offices for the facilities department. Completion is scheduled for April 24 th .
|
|